NGCP Issues Yellow Alert for Luzon and Visayas Grids Amid Power Plant Outages
NGCP Issues Yellow Alert for Luzon, Visayas Grids

NGCP Declares Yellow Alert for Luzon and Visayas Grids Following Power Plant Outages

The National Grid Corp. of the Philippines (NGCP) has placed the Luzon grid under a yellow alert status on Thursday, citing an insufficient power supply margin. This alert was officially announced in an advisory and is scheduled to remain in effect from 4 p.m. to 10 p.m. The decision follows the tripping of several critical power plants across the region, which has significantly strained the grid's operational capacity.

Understanding the Yellow Alert Status

A yellow alert is triggered when the power supply reserves drop to a dangerously thin margin above the actual demand. This situation indicates a heightened risk of potential power shortages and requires immediate attention to prevent more severe disruptions. The NGCP's declaration serves as a precautionary measure to manage grid stability and ensure that contingency plans are activated promptly.

Current Power Supply and Demand Figures

As of the latest reports, the available capacity for the Luzon grid stands at 12,223 megawatts (MW), while the peak demand is recorded at 11,996 MW. This narrow gap highlights the precarious balance between supply and consumption. The NGCP has identified that 35 power plants are currently on forced outage, and an additional 14 are operating at reduced capacity. Collectively, these issues have rendered 5,137.2 MW of power unavailable, exacerbating the supply shortfall.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Key Outages Affecting the Grid

Several major power generation facilities have contributed to the current crisis. Notable outages include Units 1, 2, and 3 of Excellent Energy Resources Inc., along with Block B of the Ilijan Power Plant located in Batangas. Additionally, the shutdown of Magat hydro units 1 through 4 in Isabela has further reduced the available power supply. These disruptions have collectively strained the grid's ability to meet the escalating energy demands.

Visayas Grid Also Under Yellow Alert

In a related development, the Visayas grid will also be placed under a yellow alert from 6 p.m. to 7 p.m. The available capacity in this region is reported at 2,597 MW, against a peak demand of 2,368 MW. According to the NGCP, 15 plants are on forced outage, and 13 are running at reduced capacity, resulting in 679.2 MW being unavailable. This alert has been partly attributed to the lack of power imports from Luzon via the high-voltage direct current (HVDC) link, which typically helps balance supply across grids.

Implications and Next Steps

The simultaneous yellow alerts for both Luzon and Visayas grids underscore the broader challenges facing the Philippines' power infrastructure. The NGCP is actively monitoring the situation and implementing measures to mitigate potential impacts. Consumers are advised to conserve energy during peak hours to help alleviate pressure on the grid. The corporation continues to work on restoring affected plants and optimizing available resources to ensure a stable power supply across the nation.