The completion of the P14.6 million skywalk in Barangay Ibo, Lapu-Lapu City, has been pushed back once more, failing to meet its revised target of November 2025. This marks the latest setback for a public infrastructure project plagued by repeated suspensions and timeline revisions.
Revised Deadlines and Persistent Delays
According to official project documents, the construction of the skywalk was initially planned for a 188-day period starting February 14, 2024, with an original completion date set for November 17, 2024. The project has since missed that deadline and several revised timelines.
Lone District Representative Junard “Ahong” Chan provided an update on December 18, 2025, confirming the latest delay. While construction activities have resumed, the November 2025 target was not achieved. The contractor, GSixty Construction Services, has now committed to finishing the project within the month of December.
Root Causes: Power Lines and Right-of-Way
The skywalk project has been a subject of public scrutiny due to multiple work stoppages. The primary causes for suspension were unresolved issues concerning overhead power lines and necessary road right-of-way clearances, which critically affected site access.
The Department of Public Works and Highways (DPWH) 6th District Engineering Office had previously acknowledged these interruptions. Officials stated that coordination with utility providers and other affected stakeholders was required before construction could proceed safely and legally.
Contractual Obligations and Potential Penalties
Rep. Chan emphasized that the Lapu-Lapu City Government has formally raised its concerns with the DPWH regarding the continuous delays. He clarified that while the city's role is limited to follow-up, the DPWH holds full authority over the project's implementation, including payments, inspections, and the imposition of penalties.
Completion of the skywalk is a firm part of the contract, Chan stated. He issued a clear warning that failure to meet the newly committed schedule will result in financial deductions and other sanctions against the contractor for any unjustified delays.
During a recent inspection with project engineers, Chan noted that progress is visible, with roofing now installed on the skywalk's steel structure. However, the community continues to wait for the full and final delivery of this long-awaited pedestrian infrastructure.